Wind Power Authorizations
The following subsection outline the key regulatory permits and approvals likely to be required from all three levels of governments. In the course of time the Environmental Report will address and provide the background on the requirements for these permits and approvals through legislation covered under the applicable acts, regulations, and planning documents.
Federal Authorizations and Permits
| Permit / Authorization |
Administering Agency |
Rationale |
| Canadian Environment Assessment |
NRCan, DFO, Transport Canada |
WPPI Funding, Issuing Permits & Authorizations |
| Aeronautical Obstruction Clearance |
Transport Canada - Aviation Division |
Turbine Marking & Lighting |
| Land-Use Clearance |
NAV Canada |
Notice to Airmen |
| Navigational Clearance |
Transport Canada - Marine Division |
Crossing a Navigable Watercourse |
| Fisheries Act |
DFO |
Harmful alteration, disruption, or destruction of fish or fish habitat |
Ontario Authorizations and Permits
| Permit / Authorization |
Administering Agency |
Rationale |
| Environmental Screening Process - Ontario Regulation 116/01/EAA |
MOE |
Electricity project approval |
| Certificate of Approval - Air |
MOE |
Environmental noise emissions |
| Archaeological Clearance |
Ministry of Culture |
Archaeological & heritage resources |
| Official Plan Amendments |
Ministry of Municipal Affairs & Housing (MMAH) |
Amendments to existing Township Official Plan |
| Planning Act - Provincial Policy Statement (PPS) |
MMAH |
Official Plan designation & Zoning By-law to be consistent with the PPS |
| Fill, Construction, & Alteration of Waterways |
Conservation Authority / MNR |
Work within floodplains |
| Encroachment Permit |
MTO |
Crossing of provincial highways |
| Land-Use Permit |
MTO |
Project works undertaken within 180m of an MTO controlled intersection |
| Commercial Access Permit |
MTO |
Ingress/egress from provincial highway |
| Change of Access & Heavy / Oversize Load Transportation Permit |
MTO |
Compliance with provincial highway traffic and road safety regulations |
| Leave-to-Construct |
Ontario Energy Board (OEB) |
Development of a HV transmission facility |
| Generator's License |
OEB |
Generator Operation Permit |
| Transmitter License |
OEB |
Transmission of electrical power to interconnect with provincial grid |
| Customer Impact Assessment |
Hydro One |
Evaluation of potential effects to existing electrical customers |
| System Impact Assessment |
IESO |
Potential effects of integrating the Project within provincial transmission system |
Municipal Authorizations and Permits
| Permit / Authorization |
Administering Agency |
Rationale |
| Official Plan Amendment |
Loyalist Township |
Policy formulation and land-use control |
| Zoning By-Law Amendment |
Loyalist Township |
Establishment of setbacks and land-use control |
| Site Plan Approval |
Loyalist Township |
Project compliance with Provincial Plan and Zoning requirements |
| Entrance Permit |
Loyalist Township |
Ingress/egress from Municipal roads |
| Building Permit |
Loyalist Township |
Compliance with Ontario Building Code |
| Land Agreement |
Hydro One |
Use of land for transmission line on mainland |
|